Here is the latest construction update for AMANI Melasti for March.

During Ramadan in Bali, construction activity traditionally slows down. Many workers travel to other islands to spend time with their families, so some processes on site are temporarily paused. This is a standard regional practice and is fully taken into account in the overall project schedule.
Construction has now resumed. The team is gradually returning to the site, and as of April 4, the project is fully back to normal operations. This will allow construction to return to a stable pace and continue in line with the planned schedule.

In April, works in Section 1 will include the installation of the second-floor slab.
In Section 2, the planned scope includes vertical structures of the first floor, installation of the second-floor slab, and horizontal waterproofing on the technical floor.
In Section 3, works will include the installation of the third-floor slab, construction of the vertical structures of the third floor, and horizontal waterproofing on the first floor.

As a result, in April the project moves into an active construction phase across several sections, and in the next update we expect to share even more visible progress from the site.