Here is the latest construction update for AMANI Melasti for March.
During Ramadan in Bali, construction activity traditionally slows down. Many workers travel to other islands to spend time with their families, so some processes on site are temporarily paused. This is a standard regional practice and is fully taken into account in the overall project schedule.
Construction has now resumed. The team is gradually returning to the site, and as of April 4, the project is fully back to normal operations. This will allow construction to return to a stable pace and continue in line with the planned schedule.
In April, works in Section 1 will include the installation of the second-floor slab.
In Section 2, the planned scope includes vertical structures of the first floor, installation of the second-floor slab, and horizontal waterproofing on the technical floor.
In Section 3, works will include the installation of the third-floor slab, construction of the vertical structures of the third floor, and horizontal waterproofing on the first floor.
As a result, in April the project moves into an active construction phase across several sections, and in the next update we expect to share even more visible progress from the site.
2026
Amani Melasti
Construction progress
News
8.4.2026
AMANI Melasti Construction Progress — March 2026

3
min read
You may be interested

2026
awards
Ramada Nusa Dua by Wyndham
Radisson Resort Maldives
15.3.2026
TEUS Group Gains International Recognition: Three International Property Awards for Projects in Bali and the Maldives
International development company TEUS Group has once again confirmed the high quality of its projects on the global stage, receiving three prestigious International Property Awards — one of the most respected awards worldwide in the fields of architecture, development, and real estate.

DESIRE Antalya
Construction progress
5.3.2026
Construction Progress of DESIRE Antalya – February 2026
We are sharing the latest updates from the DESIRE Antalya construction site for February. In Block A1, the installation of sewage and water supply pipes in the apartments has been completed. Preparatory work is underway for the start of interior finishing works.

Construction progress
Amani Melasti
News
5.3.2026
AMANI Melasti Construction Progress — February 2026
Here is the February construction update for AMANI Melasti. During the month, monolithic works were carried out simultaneously across all three sections of the complex, focusing on vertical and horizontal reinforced concrete structures.