We are pleased to share the latest updates from the DESIRE Antalya construction site for September.
Block A1. Finishing of the stairwells with marble has been completed, and marble elevator portals have been installed. Walls and ceilings in the apartments and common areas have been painted. Installation of 90% of balcony and terrace railings has been completed. Floor screeds and rough wall finishing have been completed in the shelter and technical rooms of the basement.
Block A2. Assembly and installation of elevator cabins have been completed, and elevator doors have been installed. Marble finishing of the stairwells is in progress. Glazing of the entrance area and floors 1–3 is 50% complete. Wall cladding and ceramic floor tile installation in bathrooms and corridors have been completed. Painting of walls and ceilings in apartments and common corridors is nearing completion. Installation of glass and aluminum balcony and terrace railings is in progress. Floor screeds and rough wall finishing have been completed in the technical rooms of the basement.
Block A3. Assembly and installation of elevator cabins have been completed, and elevator doors have been installed. Wall cladding and installation of ceramic tiles on the walls and floors of bathrooms and corridors are nearing completion. Painting of walls and ceilings in apartments and common corridors is in progress. Floor screeds and rough wall finishing have been completed in the shelter and technical rooms of the basement.