Here's the latest update from the Amani Melasti construction site.

In May, work advanced steadily across all three sections, and Section3 entered a new phase with the start of brickwork.

Current status:
— Section 1 — the second-floor slab has been completed, and the verticalstructures of the second floor are underway — around 80% complete.
— Section 2 — the vertical structures of the second floor and the third-floorslab have been fully completed. Reinforcement of the fourth-floor slab isunderway and around halfway complete.
— Section 3 — the vertical structures of the fourth floor are actively goingup, and brickwork has officially begun — the building is entering a newconstruction phase.

Planned works on site for June:
— Section 1 — continuation of the vertical structures, advancing to the thirdfloor.
— Section 2 — continuation of works, advancing to the fourth floor.
— Section 3 — continuation of works, advancing to the fifth floor.

We'll share new progress from the site in the next update.