We are sharing the latest updates from the DESIRE Antalya construction site for April 2026.
In Block A1, machine plastering of apartments, corridors, staircases, and technical balconies has been completed. Work is underway on the installation of suspended ceiling frameworks. Fire water supply piping has been installed. Fire cabinets have been installed in the corridors on each floor. Preparatory work is underway in the elevator shafts for the installation of guide rails.
In Block A2, machine plastering of apartments, corridors, staircases, and technical balconies has been completed. Electrical cable pulling through wiring channels in the apartments has been completed.
In Block A3, electrical cable pulling through wiring channels in the apartments has been completed. Plastering works are being carried out in the apartment bathrooms.
In the basement, preparatory work is underway for the start of ventilation and parking smoke extraction system installation works.