We are sharing updates from the DESIRE Antalya construction site for December.
In Block A1, the works on the installation of the rough facade are nearing completion. In common areas, works have begun on laying pipes for electrical cables. The installation of wiring for apartment air conditioning systems has been completed.
In Block A2, works on the installation of the rough facade are ongoing. The installation of wiring for apartment air conditioning systems is in progress.
In Block A3, roofing works have been completed. The installation of wiring for apartment air conditioning systems is ongoing.
Works on the installation of marble drip edges on window sills and balcony thresholds in Blocks A1, A2, and A3 on floors 2 through 7 have been completed.