We are sharing the latest updates from the DESIRE Antalya construction site for January.

In Block A1, works on the installation of the rough façade have been completed. Installation of sewerage and water supply pipes has begun. Works on terrace screeds have been completed.

In Block A2, works on the installation of the rough façade have been completed. Installation of the air-conditioning main lines has been completed. Works on terrace screeds are ongoing. Installation of apartment sewer risers is in progress.

In Block A3, works on the installation of the air-conditioning main lines have been completed. Installation of apartment sewer risers is in progress. Works on terrace screeds are ongoing.

Works on the installation of marble window sills and drip edges are being carried out throughout the building on the entrance floor and the first floor.