We’re sharing the July progress from the DESIRE Antalya construction site.
Block A1: walls and partitions completed up to the seventh floor level. Parapet installation on the roof has begun.
Block A2: walls and partitions completed up to the fifth floor level. Work continues on the sixth and seventh floors. Metal structures of the fire corridors have been installed.
Block A3: walls and partitions completed up to the fifth floor level. Work continues on the sixth and seventh floors.
90% of walls and partitions of the underground parking, indoor pool area, and recreation zone are complete.
Construction continues on the outdoor pool and the retaining wall around the perimeter of the site.