We are sharing the April work dynamics at the DESIRE Antalya construction site.
Block A1: columns, pylons, elevator shafts, and floors of the 5th floor are completed. The installation of column frames, pylons, and elevator shafts on the 6th floor is in progress. Work has started on the blockwork of the external walls and partitions of the 2nd and 3rd floors.
Block A2-1: all vertical structures and the ceiling of the 5th floor have been completed.
Block A2-2: all monolithic structures of the 5th floor have been completed.
Block A3: all monolithic structures of the 4th floor have been completed. Concrete columns, pylons and lift shafts of the 5th floor have been concreted. Works on formwork and reinforcement of the floor beams on the 5th floor are in progress.