3
min read
We are sharing an update from the DESIRE Antalya construction site for August.
In blocks A1, A2, and A3, 100% of the wall and partition works have been completed, including the basement. The parapet of the roof has been completed in all blocks.
The installation of metal structures for the corridors in block A2 has been finished.
A retaining wall has been built on the side of the recreation area and swimming pools.
All outdoor pools have been completed.
Works on the entrances to all blocks are ongoing, including ramps and the retaining wall on the side of block A3.
Work has begun on laying electrical networks and water supply pipes.