We are sharing the June work dynamics at the DESIRE Antalya construction site.

Block A1: columns, pylons, elevator shafts, and the slab of the 7th floor have been completed. 100% of the monolithic structures of Block A1 are done! Works on installing the walls and partitions of the 4th floor are ongoing.

Block A2-1: all vertical structures as well as the 7th floor slab have been completed. 100% of the monolithic structures of Block A2-1 are done! Works on installing the walls and partitions of the 4th floor are ongoing.

Block A2-2: all monolithic structures of the 7th floor have been completed. Works on installing the walls and partitions of the entrance floor are ongoing.

Block A3: reinforcement and formwork installation for columns, pylons, and elevator shafts of the 7th floor are ongoing. Works on installing the walls and partitions of the 1st floor are ongoing.