We are sharing the May work dynamics at the DESIRE Antalya construction site.

Block A1: columns, pylons, lift shafts, and floors of the 6th floor are completed. All the columns, pylons, and lift shafts of the 7th floor have been completed. 

Block A2-1: All vertical structures and the floor of the 6th floor have been completed. 

Block A2-2: All monolithic structures of the 6th floor have been completed. 

Block A3: All monolithic structures of the 6th floor have been completed.