We’re sharing the latest updates from the DESIRE Antalya construction site for October.
In Block A1, electrical installation works for cable ducts in the apartments have been completed. Installation of frames for underfloor heating on balconies and arrangement of water drainage systems are underway. Waterproofing of the roof is in progress.
In Blocks A2 and A3, works on the rough exterior façade are being carried out. Scaffolding is being installed in the recreation area of Block A3 for further façade works.
In Block A2, installation of conduits for cable wiring in the apartments continues.
In Block A3, stormwater drainage installation is in progress.
Works on marble window sills along the roof parapet are also ongoing. These works have been completed in Blocks A1 and A2, and are in progress in Block A3.