We are pleased to share the latest updates from the DESIRE Antalya construction site for August.

In Block A1, glazing works for apartments, staircases, and corridors have been completed.

The assembly and installation of elevator cabins have been completed. Elevator doors have been installed. Marble works on the fire escape staircase have been completed, while marble finishing works on the main staircase are ongoing. Porcelain stoneware flooring has been completed in the corridors. Painting works are underway in the apartments and common areas, including walls and ceilings. Entrance doors to the apartments have been installed.

In Block A2, work is underway on the installation of elevator entrances and the assembly of elevator cabins. Floor screed works have been completed. Glazing of the 5th–7th floors has been completed. Window frames have been installed on the 4th floor. Ceramic tile installation on walls and floors in the bathrooms and corridors of the 1st floor is ongoing. Works on the 2nd–4th floors have been completed. Painting works on walls and corridors are in progress.

In Block A3, work is underway on the installation of elevator entrances and the assembly of elevator cabins. Glazing of the 5th–7th floors has been completed. Window frames have been installed on the 4th floor.

In the basement, the installation of ventilation and parking garage smoke extraction ducts has been completed, and the equipment has been installed. Fire water supply system installation works have also been completed.