We are sharing the latest updates from the DESIRE Antalya construction site for July.

In Block A1, the installation of window frames with integrated shutters has been completed in the apartments and common-area corridors. Glazing works are approaching completion.

In Block A2, suspended ceiling installation has been completed. Elevator shaft works have been finalized, including the installation of guide rails and cabin lifting systems with hoist motors. Underfloor heating installation has also been completed. Floor screed works are currently underway on the entrance level and have already been completed on the upper floors.

In Block A3, suspended ceiling installation has been completed. Underfloor heating systems have been installed, and preparations are underway for flooring works on the entrance level. Elevator shaft works have also been completed, including guide rails and cabin lifting systems with hoist motors.

Facade painting works are nearing completion.

In the basement, work continues on the installation of parking ventilation and smoke extraction ducts, as well as the fire water supply system.