We are pleased to share the latest updates from the DESIRE Antalya construction site for May.
Block A1: Installation of gypsum board suspended ceilings has been completed. Work is ongoing in the elevator shafts, including the installation of guide rails and portal structures. Underfloor heating and floor screeding have been completed in full. Porcelain stoneware terrace coverings have been completed. 40% of the façade finishing works have been completed.
Block A2: Suspended ceiling installation works are underway on the 5th floor. The 6th and 7th floors have been completed. Corridor window structures on floors 5–7 have been installed. Elevator guide rail and portal installation works are in progress.
Block A3: Machine-applied plastering works have been completed. Suspended ceiling installation works are underway on the 5th floor. The 6th and 7th floors have been completed.
Basement: Installation of parking ventilation and smoke extraction ducts is in progress.