We are sharing updates from the DESIRE Antalya construction site for November.

In Block A1, a set of works on the installation of the roof has been completed. The walls of the parking area and technical basement rooms have been plastered.
In Block A2, work is underway on the installation of the exterior rough façade. Electrical installation work has been completed for laying cable channels in the apartments. Work is being carried out on installing frames for underfloor heating on balconies and water drainage systems. A set of works on the installation of the roof has been completed.
In Block A3, work on the installation of the exterior rough façade has been completed. Stormwater drainage installation has been completed. Roofing work is ongoing. Electrical installation work is underway to create cable channels in the apartments.
Work is also underway to install marble drip edges on window sills and balcony thresholds in Blocks A1, A2, and A3.